For the Irrigation Department, Assam

Water on the days the crop needs it, within the hours the pumps can really run.

JalSuchi gives the engineer in charge of a lift, flow or tube-well scheme a plan for the coming week: how much water each part of the command area needs, which days to run, and which outlets go first when there isn't enough. It starts from what farmers have actually sown, and the engineer approves every plan.

Flow, lift and tube-wellone plan format for all three
A range on every numberand the reasons behind it
Engineers decideJalSuchi never runs a pump
Pump house notice · Week 12Illustrative
Bechimari Lift Irrigation Scheme
Water plan for 16–22 March · approved by the Assistant Engineer, Sipajhar · hours of pumping per block
Both pumps workingPower, last 14 days: about 12½ h a dayTail block first
Thursday is on hold: rain is likely. If it doesn't come, JalSuchi will say so on Wednesday evening and the pumps run as normal.
01The problem today

The dry season is when water is needed, and when it least arrives

Most of the Department's schemes are minor ones: a pump house on a river bank, a weir with a canal, or a deep tube well. They are built to carry crops through the winter and spring, when Assam gets little rain. That is exactly when they deliver least.

In a CAG audit of 73 minor irrigation projects, the area actually irrigated in kharif was about 63% of what the projects were built for. In the rabi and pre-kharif season it was about 9%. Only one surveyed farmer in five said dry-season water came on time. The reasons recorded were familiar: worn-out schemes, erratic power, rivers changing course, damaged canals.

Sources: CAG Report on the Economic Sector, Government of Assam, year ended March 2019 (published 2021), para 2.2.7, covering April 2017 to March 2019. The Irrigation Minister told the Assembly in September 2023 that 1,585 of 3,919 schemes were not working (The Sentinel, 15 Sep 2023). The figures are a few years old; the pattern is what matters here.

The Department is bringing schemes back into service; the Minister reported 410 repaired in two years. JalSuchi works on the next step: getting a running scheme's limited pumping hours to the right fields on the right days. A week at a working lift scheme can go like this.

Monday morning

The operator checks for power, starts both pumps and opens the head outlets, as every day this season. The head fields fill first.

Monday afternoon

Power trips twice. By the time water would move on to the tail, the day's hours are gone. Farmers at the tail call the operator.

Wednesday

Nobody quite knows how much boro was transplanted this year at the tail, or whether it was more than last year. The routine stays the same.

Thursday

Twelve millimetres of rain fall in the afternoon, after the pumps have run since dawn. The head fields overflow into the drain.

Saturday

The tail boro, now at panicle initiation, has had water on two days out of six. Nothing on Monday showed that coming.

An illustrative week, drawn from the challenge statement and the Department's 2024 O&M procedure. We'll walk through the real routine with the sub-division during discovery.

02Where things stand

Every scheme is on the Department's register. JalSuchi adds the weekly water plan.

The Department already has a working digital base for its schemes and a clear operating procedure. JalSuchi builds on both and adds the piece that turns them into water on the right fields: a plan for next week, for this scheme, with these pumps.

IPMS, INO Irrigation and Khetiyak Bondhu

The Department's register of every scheme, with location, working status and beneficiaries. Officials update it through the INO Irrigation app, and farmers report problems in Assamese through Irrigation Khetiyak Bondhu.

JalSuchi reads the scheme list and status from IPMS and writes approved plans and run logs back. One register.

The 2024 O&M procedure

Sets out the operator's routine: check the power, run to a pre-planned schedule that follows the crop and the weather.

JalSuchi drafts that schedule each week, block by block, for the Assistant Engineer to approve.

The gap: next week's water, block by block

How much water a crop needs is well understood. What a scheme needs is that arithmetic turned into hours per block for the coming week, sized to the hours the feeder really gives, and changed when rain is forecast or a pump fails.

JalSuchi brings sowing, forecast, pumps and power hours into one weekly plan, and learns from every logged run.
03What JalSuchi does

Three ideas, one weekly plan

1 · Start from what's sown

The biggest unknown isn't the weather. It's how much was planted, and where.

Rabi and boro cropping changes every year with prices, labour and how the scheme did last year. A plan built on last year's area is wrong before it starts.

Before the season and again at transplanting, one person per block (the WUA secretary, or a nominated farmer where there is no working WUA) sends a short sowing return: crop, area, date. JalSuchi checks it against the latest satellite image. Where they disagree, the block is flagged and its range is widened until someone confirms.

BlockBoro, saidSatellite
A (head)9 ha9.3 haMatches
C14 ha14.6 haMatches
D (tail)11 ha last year16.8 haNo return yet
Block D's plan uses the satellite estimate, with a wider range, until the WUA confirms. Synthetic.
2 · Fit the hours you actually have

A plan that needs 16 hours of pumping is no use on a feeder that gives 12.

At a lift or tube-well scheme, what can be delivered is set by how many pumps work and how many hours the power stays on. JalSuchi learns the power hours from the operator's own log, and plans inside them.

When need is higher than what the scheme can give, it says so plainly, and proposes who goes short: crops at their most sensitive stage first, tail blocks before head blocks among equals. The engineer can change the order. If the shortage is about power, JalSuchi drafts a one-page request to the APDCL sub-division for the Executive Engineer.

Need, both pumpsShort with one pumpPower hours
Hours of pumping needed each day at Bechimari, against about 12½ hours of power. Synthetic.
3 · Every run logged, next week better

Two meter readings and one question a day. The plan learns from them.

Most schemes have no flow meter, and we don't assume one. The operator sends the hour-meter reading at start and stop, the power cuts, and whether water reached the tail outlet. That takes under a minute, on the app or by SMS.

From those logs JalSuchi works out what each block really received against what it needed, and suggests corrections: lower canal efficiency at the tail, fewer power hours than assumed, a pump giving less than its rating. The Assistant Engineer approves each change before it is used.

START 1 2 HM 4412.6
Operator · 05:42
CUT 09:10 09:55
Operator · 09:56
STOP HM 4423.9 TAIL Y
Operator · 18:20
Logged: 11.3 h, one cut of 45 min, tail reached. Block D got 92% of its need today.
JalSuchi · 18:20
Illustrative SMS format. The same log works in the app, offline.
04Fits what you have

Built around the Department's existing systems

  • IPMS stays the scheme registerScheme list, location, working status and staff come from IPMS and the INO Irrigation app. Approved plans and logged runs go back to it.
  • Farmers use the channel they haveSowing returns and "no water at the tail" reports come through Irrigation Khetiyak Bondhu or a plain SMS.
  • The O&M procedure, kept currentThe 2024 SOP asks operators to check power and run to a pre-planned schedule that follows crop and weather. JalSuchi is that schedule.
  • Engineers approve every planPlans are drafts until the Assistant Engineer approves them. Operators keep control of pumps and gates.
  • Agriculture and IMD data where sharedCrop calendars and sowing figures from the Agriculture Department; district forecasts from IMD, with an open forecast service as the fallback.
  • Power hours, in numbers APDCL can useLogged supply hours per feeder, and a short request the Executive Engineer can send when a feeder is the limit.